Yonge Street Reconstruction
The Town of Midland is rebuilding a portion of Yonge Street from Norene Street to Second Street as well as improvements from County Road 93 to King Street.
Yonge Street Reconstruction Timeline |
Yonge Street Reconstruction Project details and dates. |
October 11, 2023 - Public Information Centre |
Interested members of the public attend an Open House style engagement session. |
November 2023 - Staff Analysis |
Town staff and consultant review findings from PIC. |
December 6, 2023 - Report to Council |
Town Council receives report from staff and PIC review. |
Winter 2023/2024 - Design Consultation |
Town staff will work with consultant through design submissions. |
March 20, 2024 - Staff Report to Council |
Town Council receives report from staff with results from PIC. |
2025 - Project Start Date |
Project start date is expected to start in 2025. |
Frequently Asked Questions
What area will be affected? |
The project location is on Yonge St between Norene St to Second St. |
Why is this happening? |
|
When will construction take place? |
The above project timeline outline the present process for the Yonge Street Reconstruction. When more information becomes available the timeline will be updated and residents will be notified. |
Will there be upgrades to bike lanes? |
One of the projects included in The Town’s Multi Modal Transportation Master Plan is upgrading the current bike lanes along Yonge Street to comply with the Ontario Traffic Manual Book 18- Cycling Facilities. |
What was the Public Information Centre for? |
The Town hosted a Public Information Centre for interested members of the community to engage with Town staff and learn of various options for improving the active transportation facilities throughout the Yonge Street corridor. |
How can I find more information? |
If you are looking for more information, you can view the Yonge Street Reconstruction project presentation below or connect with our helpful staff. Contact Engineering Services. |
Yonge Street Reconstruction Presentation
The below presentation was shared at the Public Information Centre. The presentation covers project objectives, existing conditions of Yonge St, design options and more. Click here to view the full presentation.